A key vendor reports a two-week slip on a critical deliverable. What should the project manager do first?

A Escalate to the sponsor for a decision
B Assess the schedule impact, then work options with the vendor
C Add resources immediately to compress the schedule

Every option explained, right and wrong. Keep going free →

2026 ECO aligned 12-day streak Mock replay · Q47 of 180
Built for the 2026 PMP exam. The exam moved to a new Exam Content Outline on July 9, 2026, and sprintBANK's mocks, weights, and coverage all match it. See the full 26-task coverage table and what changed on July 9. Set your exam date. Your countdown and study plan adjust to it.

What's inside

Readiness score

One number from your accuracy, coverage, and mock performance.

Timed mock exams

Full-length and section mocks that mirror the real pacing, auto-aligned to your exam version, with complete replay and review.

Every option explained

Right and wrong. You learn the reasoning pattern, not the letter.

Smart review

Your misses and flagged items come back on a schedule that closes gaps before exam day.

30- and 60-day plans

One curriculum, two speeds. Every topic drilled before your first scored mock.

Scenario & case-study focus

Agile, hybrid, and predictive judgment calls, plus matching, multiple response, ordering, fill-in-the-blank, and multi-part case studies. Graphic-based and pull-down formats aren't simulated yet; everything else is practiced before you face it.

Inside the app

Real questions from the bank, exactly as you'll see them in the app.

PeopleTeam & LeadershipMULTIPLE CHOICE

A newly formed agile team is bickering, unclear on roles, and challenging each other. Per Tuckman's model, the team is in which stage, and what should the servant-leader do?

A Adjourning, begin closeout
C ✓ Storming, facilitate, coach, and help establish norms
WHY C IS CORRECT

Conflict, role confusion, and challenges are the hallmarks of Tuckman's Storming stage; the servant-leader coaches, facilitates, and helps set working agreements to progress toward Norming.

WHY A IS NOT IT

Adjourning is the disband stage at project end, not the early friction the team is showing.

YOUR READINESS

Almost there

Accuracy · coverage · mock pacing

Accuracy (45%)81%
Bank coverage (25%)24 of 26 tasks
Domain balance (20%)At exam weights
Mock score (10%)On track
SIT WHEN IT SAYS READY
PeopleMATCHING

Match each conflict-handling mode to its description.

CollaboratingBoth sides' underlying needs are fully met
CompromisingEach side concedes something for a middle outcome

Plus multiple response, ordering, fill-in-the-blank, and multi-part case studies, all drawn from the same 963-item bank.

How access works

Comparing question banks? See how to judge any bank →

Nick McGregor, founder of sprintBANK

Built by the founder, who studied on sprintBANK and passed the PMP.

Nick McGregor, MBMS, PMP, CPHQ · Why it exists · Passed June 2026 on the pre-update outline; the bank has since been rebuilt to the July 2026 ECO.

Find out if you're ready.

Start free. Upgrade when the taster convinces you.

Half price with code FOUNDER50.

(reg. $79.99 · code applied for you at checkout)

Secure checkout by Lemon Squeezy (merchant of record) · 14-day refund.

How the bank is built and audited